Project Profile
Commercial Dispute: Wrongful Termination of
Electrical Contractor at Power Plant
Electrical Contractor at Power Plant
![]() |
![]() |
Commercial dispute: contract termination of an electrical contractor during construction at a power plant in Maine. The dismissed contractor was replaced by another company who hired the first contractor's craftsmen and supervisors. The project was completed with materials already on site from the dismissed contractor. The issues involved disputed daily reports, manhour and per-unit cost calculations, overhead distribution, material markup, and lost profit for the dismissed contractor.